Construction milestones:
1979 January 29: Contract Award to Rockwell International's Space Transportation Systems Division
1980 March 30: Start structural assembly of crew module
1980 July 28: start fabrication of aft-fuselage
1980 October 1: start fabrication of mid-fuselage
1981 June 1: start fabrication of elevons
1981 June 1: start fabrication of wings
1981 July 13: start fabrication of crew module
1981 October 19: start fabrication of lower forward-fuselage
1981 November 23: start structural assembly of aft-fuselage
1981 December 9: start fabrication of upper forward-fuselage
1982 February 15: start structural assembly of crew module
1982 May 24: start fabrication of forward RCS module
1982 July 7: start structural assembly of payload bay doors
1982 October 4: start fabrication/assembly of vertical stabilizer
1982 November 12: start fabrication of OMS/RCS pods
1983 March 14: start fabrication/assembly of body flap
1983 May 6: Mid-fuselage on dock, Palmdale, arrived from General Dynamics
1983 June 13: Wings on dock, Palmdale, from Grumman
1983 June 17: elevons on dock, Palmdale
1983 November 7: lower forward-fuselage on dock, Palmdale
1983 December 2: payload bay doors on dock, Palmdale
1983 December 2: Start of final assembly
1984 January 6: upper forward-fuselage on dock, Palmdale
1984 January 20: body flap on dock, Palmdale
1984 February 17: left hand OMS/RCS pod on dock, Palmdale
1984 February 24: right hand OMS/RCS pod on dock, Palmdale
1984 March 16: aft-fuselage on dock, Palmdale
1984 April 9: crew module on dock, Palmdale
1984 April 24: upper forward-fuselage on dock, Palmdale
1984 April 27: forward RCS on dock, Palmdale
1984 May 25: Final assembly and closeout installation, Palmdale
1984 May 28: start initial subsystem test, power-on, Palmdale
1984 August 10: complete initial subsystem test, power-on, Delta F, Palmdale
1984 October 26: complete subsystem tests, Palmdale
1985 March 6: Rollout from Palmdale